Only one track in use at Myllypuro Metro station from 15 June

Only one track will be in use at the Myllypuro Metro station during the summer. The Metro will run every 10 minutes between Mellunmäki and Ruoholahti and between Vuosaari and Ruoholahti. On the Itäkeskus - Ruoholahti line, the Metro will run every five minutes.

The track in the direction of Ruoholahti will be closed from Monday 15 June. The Metro will use the track in the opposite direction from 15 June to 13 July. In other words, the Metro will use the same track in both directions. The track is closed because of tiling work.

In mid-July, the works will continue on the opposite side of the platform. The track in the direction of Mellunmäki will then be closed and the Metro will use only the track in the direction of Ruoholahti for about one month from mid-July. The tiling work will be completed in August.

New entrance to be completed in the summer

A new northern entrance will be opened at the Myllypuro station in the summer. The new entrance will be next to the Jauhokuja bridge. Once the construction work is completed, the platform level can be accessed from Jauhokuja by two new lifts and a staircase.  

Once the northern entrance is completed, works will continue in the Myllyaukio side of the station with renovation of the ticketing hall. The Myllyaukio entrance will be closed during the renovation. Access to the platforms will be via the northern entrance and stairs from Myllypurontie. Accessible entrance will be at the north end of the station (Jauhokuja). The renovation will be completed in spring 2016.